ANALISIS RISIKO DALAM SUPPLY CHAIN PROYEK KONSTRUKSI MENGGUNAKAN METODE HOUSE OF RISK

Aulia Dewi Ambarsari, Felicia Tria Nuciferani, Siti Choiriyah, Feri Harianto, Devi Indah Permatasri, Mila Kusuma Wardani

Abstract


During the construction process of the Sidoarjo Funeral Home, issues related to material flow led to project delays and deviation from the planned schedule. Therefore, risk analysis and evaluation are crucial to address potential disruptions in the material flow. This study applies the House of Risk (HOR) method to identify, prioritize, and develop mitigation strategies for risks arising within the material flow process. The risk identification phase adopts the Supply Chain Operation Reference (SCOR) approach to determine risk events and their causes. Subsequently, calculations are conducted to prioritize risk agents and design appropriate mitigation strategies. The strategy formulation process begins by assessing the correlation between mitigation actions and risk agents, followed by the calculation of Total Effectiveness (TEk), Degree of Difficulty (Dk), and the Effectiveness to Difficulty Ratio (ETDk) to determine the ranking of mitigation priorities. The results of the study identify 19 risk events and 20 associated risk causes within the material flow. Eight mitigation strategies are proposed to address nine dominant risk causes, including: the development of Standard Operating Procedures (SOPs) as a communication system, adding security protection for materials, conducting punishment to related parties, creating an integrated system, coordinating and communicating with suppliers, making agreements with external parties, conducting training, and tightly selecting workers.

Keywords


House of Risk (HOR); Supply Chain; Supply Chain Operation Reference (SCOR); Risk Management

Full Text:

PDF

References


A. Fendi, & E. Yuliawati. (2012). Analisis Strategi Mitigasi Risiko pada Supply Chain PT. PAL Indonesia (Persero. SEMINAR NASIONAL APLIKASI SAINS & TEKNOLOGI (SNAST) PERIODE III.

Ariani, D. W. (2004). Pengendalian Kualitas Statistik (Pendekatan Kuantitatif dalam Manajemen Kualitas). ANDI.

Cahyani, Z. D., Pribadi, S. R. W., & Baihaqi, I. (2016). Studi Implementasi Model House of Risk (HOR) Untuk Mitigasi Risiko Keterlambatan Material Dan Komponen Impor Pada Pembangunan Kapal Baru. Jurnal Teknik ITS, 5(2). https://doi.org/10.12962/j23373539.v5i2.16526

Hendricks, K. B., & Singhal, V. R. (2003). The effect of supply chain glitches on shareholder wealth. Journal of Operations Management, 21(5), 501–522.

Nyoman Pujawan, I., & Geraldin, L. H. (2009). House of risk: a model for proactive supply chain risk management. Business Process Management Journal, 15(6), 953–967. https://doi.org/10.1108/14637150911003801

Perwiranegara, A. F., Wibowo, K., & Mudiyono, R. (2024). STRATEGI MANAJEMEN RESIKO PADA PROYEK PENGENDALIAN BANJIR DAN ROB SUNGAI LOJI – BANGER PAKET 1. Jurnal Teknik Sipil Giratory UPGRIS, 5(2), 132–140. https://doi.org/10.26877/giratory.v5i2.21968

Sherina, A. E. (2021). Usulan Perancangan Mitigasi Risiko Rantai Pasok Menggunakan Metode House Of Risk (Studi Kasus pada UKM Maketees). Universitas Islam Indonesia.

Sibuea1, M. E., & Saragi, H. S. (2019). Analisis Risiko Keterlambatan Material dan Komponen pada Proyek Pembangunan Kapal dengan Metode House of Risk (HOR) Studi Kasus: Pembangunan Kapal Ro-Ro 300 GT Danau Toba. Jurnal Sistem Teknik Industri, 21(2). https://doi.org/10.32734/jsti.v21i2.1217




DOI: https://doi.org/10.26877/giratory.v6i2.27918

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Teknik Sipil Giratory UPGRIS

Program Studi Teknik Sipil

Fakultas Teknik dan Informatika

Universitas PGRI Semarang